NDA Members JR Ramone, OilQuick Meet Deadline With Time to Spare
				NDA News
				On: May 09, 2019 | By: NDA 
			 
		 
		
	 
		
		
		
			
		On March 1, the intersection was closed at 9 p.m. JR Ramon had a total of 40 crew members over four 12-hour shifts, working continuously until the job was complete — the 12-hour requirement was met with an hour to spare.The overall demolition phase was completed in 34 hours, 19 hours ahead of schedule. Read more here.
		
		
		
		