NDA Costello Dismantling demolishes a garage in residential South Boston
				NDA News
				On: May 21, 2019 | By: NDA 
			 
		 
		
	 
		
		
		
			
		Prior to the start of the dismantling work, Sea and Shore installed augured piles and a shoring system to support the brick walls of the garage, which were to remain in place after the removal of the remaining structure. Costello provided hand labor, working from manlifts, to bring the exterior brick walls to a new desired elevation. Interestingly, the piling and support system was engineered to allow excavation within the building footprint for planned underground parking. Parking spaces created off-street and below grade were an extremely valuable component to this project. Read more here.
		
		
		
		
	 Back to Demolition Insights Home