Judge Orders New Orleans, Hard Rock Developer to Decide on Demolition
Safety
On: April 30, 2020 | By:
A judge has set an April 29 deadline for the city of New Orleans and the developer of the Hard Rock Hotel to take action on a proposal to remove two bodies that remain in the partially collapsed building and bring down its upper floors by July.
Attorneys for the developer, 1031 Canal Street Developer LLC, filed a motion the week of April 20 for the city to approve the plan. The plan involves using cranes with wrecking balls, shears and other tools to pick apart and dismantle the structure from the top down. It would also require the removal of two adjacent historic buildings.
Read more in the article below.